QFR-2027-0143
Constellation-class (FFG-62) construction schedule and design stability
SASC · SSIC 5216 · Suspense 2026-07-21
Part a.
What is the current status of Constellation-class construction, and what measures reduce design churn and downstream rework on the lead ship?
ETMS2
ETMS2-1180251
Hearing
S.Hrg. 119-114, Subcommittee on Seapower, 11 Mar 2026
Received
2026-07-07
OPR
N83
OCR
N80
N80
Concur — figures align to PB-2027 extract.
Drafted from the question, guidance library, and prior answers. Edit before it enters coordination — every save is audited.
**Response to QFR from Sen. Kestrel — Constellation-class Schedule** Lead-ship construction is proceeding, with design-stability measures in place to reduce rework and support a more predictable delivery profile.¹ The Navy is holding the design baseline and sequencing production to protect downstream hulls, consistent with guidance to stabilize surface-combatant procurement in support of the industrial base.² Illustrative procurement and advance-procurement lines for FY2027 surface combatants reflect this approach.³
- [1] g6
- [2] g3
- [3] g7
The draft is unlocked once required inputs return from OCR offices. Auto-suggested from question NLP.
N80/Industrial Base
Confirm supplier count for critical sub-assemblies.
Due 2026-07-14
Program office
FY2027 planned procurement rate + rough delta vs. PB.
Due 2026-07-16
N81/Assessments
Schedule-risk narrative if throughput flat.
Due 2026-07-15
No downward data calls opened. Use this when Navy equity requires input from a subordinate/supporting command (CNSP, CNAF, NAVSEA PEO Ships, NAVSUP, CNIC, MSC, NAVFAC).
Multi-office clearance. Counsel + Security + Comptroller gates trigger conditionally on content.